Respuesta :
Answer:
Calculations are below
Explanation:
mean = 21
s.d = sqrt(4) = 2
a.) P(X<17) = P(Z<(17-21)/2) = P(Z<-2) = 1 - 0.9772 = 0.0228
b.) P(X<20) = P(Z<(20-21)/2) = P(Z<-0.5) = 1 - 0.6915 = 0.3085
c.) P(X<23) = P(Z<(23-21)/2) = P(Z<1) = 0.8413
d.) P(X<25) = P(Z<(25-21)/2) = P(Z<2) = 0.9772
e.) P(X<x) = 0.95
z = 1.645
(x - 21)/2 = 1.645
So x = 24.29
SO 24.3 months
Probability is the chance of an event occurring. The due date that yields a 95% chance of completion is 24.3.
Given to us
Variance, v = 4
Expected time, μ = 21 months
We know that variance is the squared value of the standard deviation, therefore,
[tex]v = \sigma^2\\\sigma^2 = 4 \\\sigma = 2[/tex]
A.) x = 17 months
The probability of the project getting complete in 17 months,
[tex]P (z = x) = \dfrac{x-\mu}{\sigma}\\\\P (z = 17) = P(z=\dfrac{17-21}{2})\\\\P (x = 17) = P(z = -2)\\[/tex]
Using Z-table,
P(z = 17) = 0.0288 = 2.88%
B.) x = 20 months
The probability of the project getting complete in 20 months,
[tex]P (z = x) = \dfrac{x-\mu}{\sigma}\\\\P (z = 20) = P(z=\dfrac{20-21}{2})\\\\P (x = 20) = P(z = -0.5)\\[/tex]
Using Z-table,
P(z = 20) = 0.3085= 30.85%
C.) x = 23 months
The probability of the project getting complete in 23 months,
[tex]P (z = x) = \dfrac{x-\mu}{\sigma}\\\\P (z = 23) = P(z=\dfrac{23-21}{2})\\\\P (x = 23) = P(z = 1)\\[/tex]
Using Z-table,
P(z = 23) = 0.5398 = 53.98%
D.) x = 25 months
The probability of the project getting complete in 25 months,
[tex]P (z = x) = \dfrac{x-\mu}{\sigma}\\\\P (z = 25) = P(z=\dfrac{25-21}{2})\\\\P (x = 25) = P(z = 2)\\[/tex]
Using Z-table,
P(z = 25) = 0.9772 = 97.72%
E.) P(z = x) = 95%
Using the Z-table,
[tex]P (z = x) = \dfrac{x-\mu}{\sigma}\\1.65= \dfrac{x-\21}{2}\\\\3.3= x -21\\\\x = 24.3[/tex]
Thus, the due date that yields a 95% chance of completion is 24.3.
Learn more about Probability:
https://brainly.com/question/795909