Answer:
C) 37.7 hours
Explanation:
It is a time period which shows a delivery time to dispatch the product to the end consumer
The computation of the throughput time is shown below:
= Wait time + Move time + Queue time + Process time + Inspection time
= 28 + 3.2 + 5.1 + 1.0 + 0.4
= 37.7 hours
It is a combination of the wait time, move time, queue time, process time, and the inspection time.