At Eady Corporation, maintenance is a variable overhead cost that is based on machine-hours. The performance report for July showed that actual maintenance costs totaled $12,550 and that the associated rate variance was $390 unfavorable. If 6,400 machine-hours were actually worked during July, the standard maintenance cost per machine-hour was:

Respuesta :

Answer:

$1.9 per MH

Explanation:

Since the associated rate variance is unfavorable, that amount must be subtracted from the actual maintenance cost in order to obtain the standard maintenance cost (SMC):

[tex]SMC = \$12,550 - \$390\\SMC = \$12,160[/tex]

During July, 6,400 machine-hours were actually worked, so the standard maintenance cost per machine-hour was:

[tex]\frac{\$12,160}{6,400} = \$1.9[/tex]

The cost was $1.9 per MH