Answer:
The correct answer is D.
Explanation:
Giving the following information:
Materials handling $27,000
Direct materials $3,000 Direct labor (600 hours) $9,000 Number of material moves 4
Expected activity for the four activity drivers that would be used are: Machine hours 5,000 Material moves 600 Setups 200 Quality inspections 1,000
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 27,000/600= $45 per material move
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 45*4= $180