Answer:
$33.33
Explanation:
The computation of the predetermined overhead rate is shown below: In this question, we have to apply the formula that is presented below:
Predetermined overhead rate = (Total estimated overhead) ÷ (estimated direct labor-hours)
= $2,500,000 ÷ 75,000 direct labors hours
= $33.33
Simply we divide the anticipates total overhead by the anticipated direct labor hours