Tony has realized that two activities (A and B) in his project cannot be done at the same time because not enough resources are a days. Activity B has 2 slack vailable. Activity A is critical and has a duration of 5 should be scheduls days of slack and a duration of 2 days. How will he decide which activity
A. He should schedule activity A first
B. He should schedule activity B first
C. He should schedule both activities A and B at the same time
D. He should schedule the activity with the least cost
E. None of the above is feasible

Respuesta :

Answer:

He should schedule the activity with the least slack, that means the activity B.

So, B. He should scheduel activity B first.

He should decide the activity to be schedule first by scheduling the activity with the least slack.

Usually, the scheduling of the least variable before other with high variable will save energy and resources as they will be distributed across both variables.

Hence, the best option to decide the activity to be schedule first is by scheduling the activity with the least slack.

Therefore, the Option B is correct.