Answer:
The correct answer is D.
Explanation:
Giving the following information:
Budgeted production 7,400 units Standard machine-hours per unit 6.6 machine-hours Standard lubricants rate $ 3.50 per machine-hour
Actual production 7,600 units Actual machine-hours (total) 49,840 machine-hours Actual lubricants cost (total) $ 179,821
Manufacturing overhead spending variance= (standard rate - actual rate)* actual quantity
Manufacturing overhead spending variance= (3.5 - 3.607965)*49,840= 5,381 unfavorable