Answer:
Possible transportation modes are discussed below in detail.
Explanation:
• Purchase Request: 12 - 25 days
• Process buy request abroad: 10 - 20 days.
• Manufacturing process: 60 days
• Transport from plant to port: 1-14 days
• Paperwork: 5 - 10 days
• Wait for the container: 1 - 7 days*
• Load compartments: 3 - 6 days
• Ship days: 28 days
• Custom clearance: 7 – 14 days
• Warehouse transportation: 1-3 days
Delivery time is around 136 minimum days and 191 maximum days. Likewise, the average delivery time is 163 days. Companies such as international trade specialist, trade logistics companies and Internet exchanges can help the company to reduce the delivery time by facilitating the trade channels. These intermediate channels can help to attain objectives in timely manner.