Answer:
Overhead Rate for current year=$7 per machine hour
Step-by-step explanation:
Overhead Cost=$700000
Machine Hours Budgeted=100000
In order to calculate the Pinnacle's factory overhead rate for the current year we will consider the following formula:
Overhead rate for the current year=Budgeted overhead cost for the current year/Machne hours budgeted
[tex]Overhead rate for the current year=\frac{700000}{100000}[/tex]
Overhead Rate for current year=$7
So Pinnacle plantwide factory overhead rate for the current year is $7 per machine hour.