Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 34,400 +$ 13,700 +$ 13,700 +$ 13,700 B − 34,400 0 0 + 43,200 a. At what interest rates would you prefer project A to B?

Respuesta :

Answer:

7.89%

Explanation:

We can find the IRR of Project A and Project B is 9% and 8% respectively

(please see the calculation in excel in attachment)

So if the interest rate below 8% then Project A is more profitable than project B.

You can find NPV of each project follow the decrease in interest rate in the excel attached.