Answer:
b. They are used to identify the use of fixed resources or costs over a segment of a project.
Explanation:
Hammock activity is a project planning or a schedule term for grouping of tasks that are having a deadline.It also contains the resources that we will be needing for the project and also the cost for the project.Hence the answer is option B.