Answer:
c. $ 760,000
Explanation:
For computing the cost of goods manufactured, we have to use the formula which is shown below:
Cost of goods manufactured= Beginning work in process + manufacturing cost - ending work in process
= $125,000 + $835,000 - $200,000
= $760,000
Beginning work in process + manufacturing cost is called total work in process for a given period