Answer:
$6,200
Explanation:
The total cost assigned to this job will be computed by summing up the direct costs and overhead costs.
Direct material = $4,000
Direct labor = $1,200
Overhead costs (100 direct labor-hours X $10 overhead rate) = $1,000
Total cost assigned to Job X23 = $6,200