Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 70,000 Total fixed manufacturing overhead cost $ 273,000 Variable manufacturing overhead per direct labor-hour $ 6.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 50 Total direct labor-hours 100 Direct materials $ 680 Direct labor cost $ 7,000 The unit product cost for Job P951 is closest to: (Round your intermediate calculations to 2 decimal places.)

Respuesta :

Answer:

$5625.60

Explanation:

number of units produced =50 units

direct labour hours 100

direct materials $ 680

Direct labor cost $ 7,000

The unit product cost for Job P951 is;

Direct materials = $ 680

Direct labor cost $ 7,000

variable manufacturing overheads $ 6.00*100=600

total fixed manufacturing overheads= $ 273,000

total costs=$(680+7000+600+273000)=$281,280

unit product cost=$28,1280/50

=$5625.60