Answer:
it wll apply 335 dollars of overhead
Explanation:
Assembly rate: 45 dollars per machine hour
Sanding rate 15 dollars per labor hour
On assembly we will only follow the machien hours to apply the overhead rate
On sanding we will apply based on labor hours on that department, we will ignore the rest.
Job 603
Machine hours on Assembly: 4 x 45 = 170
Labor hours on Sandings: 11 labor hours x 15 = 165
applied overhead using the deparmental overhead rate: 335