A process produces​ 6,000 units of output that yield​ $5.00 per unit. Resources contributed to this output are 200 hours of labor at​ $15.00 per​ hour, materials at​ $750, and overhead at​ $250. What is the labor productivity​ (in units per​ labor-hour)?

Respuesta :

Answer:  30 units per hour

Explanation:

Given that,

Total number of product = 6,000 units

Yield = $5.00 per unit

Resources contributed to this output = 200 hours of labor at​ $15.00 per​ hour

Materials =​ $750

Overhead =​ $250

Labor productivity​ = [tex]\frac{Total\ number\ of\ product}{Resources\ contributed}[/tex]

                              = [tex]\frac{6,000}{200}[/tex]

                              = 30 units per hour