Answer: Option (B) is correct.
Explanation:
Given that,
High level of activity = 120,000 units
Low level of activity = 40,000 units
Utility costs = $60,000 in June
Utility costs = $156,000 in November
Variable cost per unit:
= [tex]\frac{Change\ in\ total\ cost}{High\ minus\ low\ activity\ level }[/tex]
= [tex]\frac{156,000 - 60,000}{120,000 - 40,000}[/tex]
= $1.2 per unit
Fixed cost element:
= Total cost at high level - variable cost at high level
= $156,000 - $1.20 x 120,000 units
= $156,000 - $144,000
= $12,000
Utility cost for a month:
= Fixed cost per month + $1.20 variable cost per unit at 80,000 units
= $12,000 + $1.20 x 80,000 units
= $108,000