Answer:
C. Both A and B
Explanation:
Operation Costing:
is the acccount of process costing until there is a split-point when the costing systems moves to job system.
This means the materials are calculate with calculate with process costing. And then there is a degree of customization which makes the job costing useful.
(A) FALSE is the other way around. The system use process costing until split point, when it switch to job costing for specific procedures.
(B) FALSE
An automobile manufacturer do the same car over and over.
There is no difference between the car. It will use process costing.