Answer:
The correct answer is True.
Explanation:
Whenever a conflict arises within the classification of projects between the expected monetary value and the standard deviation, the coefficient of variation is used to try to solve the problem. For this reason, it is concluded that the coefficient of variation is a standardized measure of risk.