Answer:
The variance estimate of this activity is 4.
Step-by-step explanation:
Given information: One of the activities on the critical path has
Optimistic time = 5 minutes
Most likely time = 6 minutes
Pessimistic time = 17 minutes
The variance estimate of a activity is
[tex]\sigma ^2=(\frac{t_p-t_o}{6})^2[/tex]
where, [tex]t_p[/tex] is pessimistic time of that activity and [tex]t_o[/tex] is optimistic time of that activity.
The variance estimate of the given activity is
[tex]\sigma ^2=(\frac{17-5}{6})^2[/tex]
[tex]\sigma ^2=(\frac{12}{6})^2[/tex]
[tex]\sigma ^2=2^2[/tex]
[tex]\sigma ^2=4[/tex]
Therefore the variance estimate of this activity is 4.