Answer:
4.74 hours
Step-by-step explanation:
Given that both person have to place same number of rivets that is
11209
first person take 9 hours to complete the work
hence 1 hour work of 1st person is [tex]\frac{1}{9}[/tex] of total work
second person takes 10 hours to complete the same work
hence 1 hour work of 2nd person is [tex]\frac{1}{10}[/tex]
Now if both work together then
1 hour work of both person = [tex]\frac{1}{9} +\frac{1}{10}[/tex] =[tex]\frac{19}{90}[/tex]
thus working together they need [tex]\frac{90}{19}[/tex] hours = 4.74 hours to complete the whole work which is placing 11209 rivets