Answer:
[tex]\left[\begin{array}{cccc}-&Budget&Variance&Actual\\IL&10,000&700&9,300\\IM&11000&-3,800&14,800\\Utilities&7,400&-2,400&9,800\\Maintenance&6,000&1,200&4,800\\Total \: Variable&34,400&-4,300&38,700\\Supervisor&35,400&0&35,400\\Depreciation&7,100&0&7100\\PT and insurance&7,700&-600&8,300\\Maintenance&6,000&0&6,000\\Total \: Fixed&56,200&-600&56,800\\Total \: MO&90,600&-4,900&95,500\\\end{array}\right][/tex]
Explanation:
We list them and subtract budget - actual
When actual is greater than budget the variance is negatine.
While budget being lower than actual is considered a positive variance.