Answer:
18,500 WIP balance at September 30th
Explanation:
Job A3B
3,500 direct materials
5,000 direct labor
10,000 Overhead (200% of labor = 5000 x 200%)
18,500 WIP balance at September 30th
The cost added during October will be part of October calculation, on September we should work with September values.