Respuesta :
Answer:
Finish to Start.
Explanation:
Finish to Start dependency also known as FS is most commonly used dependency type used between activities in PDM(Precedence Diagramming Method).For example :- in a software you cannot test a screen before it is developed,in construction you cannot paint a building before it is constructed. So we conclude that Finish to start is most commonly used.