Respuesta :

Answer:

Finish to Start.

Explanation:

Finish to Start dependency also known as FS is most commonly used dependency type used between activities in PDM(Precedence Diagramming Method).For example :- in a software you cannot test a screen before it is developed,in construction you cannot paint a building before it is constructed. So we conclude that Finish to start is most commonly used.

Answer:

Finish to start

Explanation:

I looked it :) hoped it helped