Answer:
Cost per unit for Job 397 = $15.12
Explanation:
Provided overhead predetermined rate = $11 based on Direct Labor Hours,
Therefore overheads will be charged on such predetermined rate.
Cost of direct material = $46,000
Cost of Direct Labor = $12 X 630 = $7,560
Cost of Overhead = $11 X 630 = $6,930
Total cost of units produced = $60,490
Total number of units produced of the Job 397 = 4,000 units
Cost per unit for Job 397 = $60,490/4,000 = $15.12