14 workers, working at the same pace, can lay 36000 bricks in one day. How many workers will be needed to lay 54000 bricks in the same period of time?

Respuesta :

[tex]\bf \begin{array}{ccll} workers&bricks\\ \cline{1-2} 14&36000\\ x&54000 \end{array}\implies \cfrac{14}{x}=\cfrac{36000}{54000}\implies \implies \cfrac{14}{x}=\cfrac{2}{3} \\\\\\ 42=2x\implies \cfrac{42}{2}=x\implies 21=x[/tex]

Answer:

21 workers would be your answer.