Work Shown:
1 yard = 3 feet
1 cubic yard = 27 cubic feet (cube both sides)
We will use this conversion factor later.
6 inches = 1/2 ft = 0.5 ft
So this slab is 16 ft by 16 ft by 0.5 ft leading to a volume of 16*16*0.5 = 128 cubic feet
Going back to the conversion factor, we can use that to help go from "cubic feet" to "cubic yards"
128 cubic feet = (128 cf)*(1 cy/27 cf) = 128/27 = 4.74 cubic yards
This slab is roughly 4.74 cubic yards. Round up to the nearest whole number to get 5 cubic yards.
Since it costs $58 per cubic yard, this means the total price comes to
5*58 = 290