Respuesta :
Answer: The answer is 12 days.
Step-by-step explanation: Given that a team of workers had to produce 54 parts daily in order to complete an assignment by a given deadline.
Let 'x' be the number of days in which the work should be finished.
The, the number of parts they are to make = 54x parts.
Also, if they make 6 extra parts each day, then the work will finish 1 day earlier with 18 extra parts, so we have
[tex](54+6)(x-1)-18=54x\\\\\Rightarrow 60(x-1)=54x+18\\\\\Rightarrow 60x-60=54x+18\\\\\Rightarrow 60x-54x=18+60\\\\\Rightarrow 6x=78\\\\\Rightarrow x=13.[/tex]
Therefore, the team worked for 13-1=12 days.
Thus, the number of days is 12.
The team works for a total of 12 days to fulfill an assignment and this can be determined by forming the linear equation in one variable.
Given :
- To fulfill an assignment by a given deadline, a team of workers had to produce 54 parts daily.
- Exceeding the schedule by 6 parts per day, the team not only finished the assignment 1 day earlier but also produced 18 extra parts.
To determine the number of days team work, first, let the total number of days be 'a'.
Now, if they make 6 extra parts per day, the team not only finished the assignment 1 day earlier but also produced 18 extra parts. So, the linear equation becomes:
[tex](54+6)(a-1)-18=54a[/tex]
[tex]60(a-1)-18=54a[/tex]
60a - 60 - 18 = 54a
6a = 78
a = 13
So, the team worked for 13 - 1 = 12 days.
For more information, refer to the link given below:
https://brainly.com/question/22122594