Respuesta :

Answer:

12.5 hours

Step-by-step explanation:

15/6 is 2.5. 2.5 is how many hours per worker. 5 times 2.5 is 12.5 hours

Answer:

12.5 hrs

Step-by-step explanation:

 We have given that:  6 painters can paint the fence in 15 hours

To find : In how many hours 5 workers do the job

Solution : 6 workers can paint the fence in = 15 hours

                1 worker can paint the fence in = 15/6  hours

                 5 workers can paint the fence in = 5×15/6 hours

                                                                       =25/2  hours

                                                                      =12.5  hours