A project cpm has a critical path of bdeg. activity e is assumed to be 6 days. your analysis suggests that there is a 10% probability that activity e will take 4 days, a 50% probability e will take 5 days, a 30% probability activity e will take 6 days, and a 10% probability activity e will take 7 days. what is the expected effect on the project duration?