Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once. What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier?

Note: There are 2 correct answers to this question.


A. Set a maximum lot size in the quota arrangement item and activate the lx checkbox
B. Assign a rounding profile in the material master record of the planned material
C. Set a maximum quota quantity in the quota arrangement item for each supplier
D. Assign the indicator for quota splitting to the lot-sizing procedure being used