Following details regarding cost estimate of a project is given:

Optimistic cost = $ 8,000
Most likely cost = $ 10,000
Pessimistic cost = $ 15,000

Calculate the three-point estimate using triangular distribution.

a) $5,500
b) $10,500
c) $50,500
d) $11,000