During project execution, one task is interrupted due unavailability of resources and must be rescheduled (reschedule date). The task does not have any actual work recorded for it and does not have a constraint applied to it. In this case:
A. The entire task is rescheduled to begin after rescheduled date
B. The task is split so that all remaining work starts after the rescheduled date.
C. Rescheduling the task will change the critical path.
D. The task is not affected.