You are appointed to recover a project which has experienced several failures. You must forecast future activities. What is the ideal time period for your forecast?
A) Two weeks: "Agile sprints"
B) Daily stand-up meetings
C) Three or more months
D) Manageable deliverables within the next 1-10 days