Which the following is true regarding scope monitoring?
a.Project managers usually start a new project to create a requested deliverable rather than change the scope.
b.Scope can be increased without affecting the budget, but it usually affects the schedule.
c.Scope changes can result from additional requirements added to deliverables from stakeholder requests.
d.Scope can be increased without affecting the schedule, but it usually affects the budget.