Which of the following will correctly calculate the free slack in an activity?
a) Late finish of the activity - Late start of the next activity
b) Late start of the activity - Early start of the activity
c) Late finish of the predecessor - Early start of the successor
d) Minimum early start of all the successors - Early finish of the activity
e) Either LS - ES or LF - EF