If the applicant chooses to have FEMA complete the scope of work and cost estimate on their behalf, FEMA will have all of the following responsibilities throughout the formulation process, except?
1) Reviewing the applicant's documentation
2) Conducting site visits
3) Preparing the scope of work and cost estimate
4) Approving the applicant's funding request