In variance analysis, measuring accomplishments centers on two key computations. Identify the two computations.
a) Budgeted cost of work performed (BCWP) and actual cost of work performed (ACWP)
b) Planned value (PV) and earned value (EV)
c) Actual cost (AC) and cost variance (CV)
d) Schedule variance (SV) and cost variance (CV)