Your team has started testing a deliverable, with the customer observing the process. Unfortunately, the testing has uncovered many defects, which are all being noted and submitted back to the appropriate technical team members to fix. Some of these fixes have an impact on the project, and you are performing an impact analysis and submitting the request to the Change Control Board (CCB). Which of the following statements is correct?
a) The defects should be ignored to avoid delays in the project.
b) The impact analysis is unnecessary; defects can be fixed without assessing their consequences.
c) The change control board (CCB) is not involved in handling defects.
d) Submitting the impact analysis and change request to the Change Control Board (CCB) is a standard practice for managing changes and ensuring proper evaluation.