A 120/240-volt, 1-ph, 3-wire service is to be run to serve 400-A, main breaker Panel B. As shown, two parallel conduits will be installed for the service. Panel B supplies 200 amps of 240-volt loads. Additionally, 122 amps of 120-volt loads are connected to AØ, and 188 amps of 120-volt loads are connected to BØ in Panel B. The BØ conductor in each of the parallel conduits will carry ___ amps.
Select one:
a.144
b.188
c.388
d.94
e.194