1.Given the following information, sketch out the network diagram.
2. Identify the different network paths through the project.
3. What is the critical path? How many days is the critical path?
Task Duration Predecessor
A 3
B 5 A
C 12 A
D 9 B
E 14 C
F 3 B
G 4 D
H 7 F, G
I 2 E, H