What falls outside of a project manager’s responsibility when integrating/coordinating tasks during the Executing, Monitoring and Controlling of a capital construction project?
A) Implementing standards and processes as planned
B) Forecasting whether the project will stay on schedule
C) keeping records on schedule, cost, progress and quality
D) Creating project charter and objectives documents