Twenty percent of the work was completed in a project. At this stage, the project manager determined that the budget at completion (BAC) was no longer viable and developed a forecasted Estimate at Completion (EAC). What index can the project manager use to look at the calculated projection of cost performance that must be achieved on the remaining work