Which of the following statements is correct about Pareto diagram?
a. It is based on the 80/20 rule.
b. It is only used for finding the causes of problems.
c. It can help in reducing the costs for projects.
d. All of the above are correct.
Which of the following can assist in levelling the workload of a team member?
a. Gantt chart
b. Cost baseline
c. Resource histogram
d. Time baseline