You are the project manager for a software consulting firm that is developing a new software program for a customer in another country. Things seem to be progressing well. Recently, your stakeholders examined the work of the project and formally accepted the work results. Which process was just performed? Manage Assurance • Close Project or Phase . Validate Scope • Control Quality 33-Which of the following is TRUE about the development of a project charter? . The project team creates the project charter, and the PMO approves it . The project manager creates the project charter, and the sponsor approves it . The sponsor creates the project charter, and the project manager approves it The executive manager creates the project charter, and the functional manager approves it 34-Changes in organizational size or structure and the introduction of new technologies are examples of . Disruptive changes • Planned changes • Demographic changes • Unplanned changes 35- An end-user needs analysis and assessment project can take many forms. An assessment project is all the following EXCEPT? Can be formal or informal . Can result in the selection of a product • Can result in the selection of a service • Can result in the selection of the appropriate project plan 36-within an origination, rules and regulations are examples of which type of interface? . Resource • Functional • Organizational • Knowledge 37- All the following are inputs to develop the project charter EXCEPT? . Benefits management plan . Business case • Project statement .. Contacts 38- An activity with zero duration that is used to determine the activity accomplishment of work products after being reviewed for quality and approved is . Work package . Outcome . Module . Milestone