Immediate Predecessor(s) A 3 B 6 A с 9 A D 11 A E 5 A F 12 B,C G 11 D,E H 3 F.G What is the overall duration of the project (in weeks)? Number weeks What is the earliest week you could start activity H? (Write the week number in the field below.) Number What is the earliest week you could finish activity F? Number What is the latest week you could start activity A? Number What is the latest week you could finish activity C? Number What is the slack time for activity B?