Using the priority list T2, T7, T6, T10, T8, T3, T4, T5, T₁, T9, schedule the project below with three processors. T1 (4) T2 (12) T3 (10) T4 (3) T6 (6) T7 (8) T5 (5) Task 5 is done by Select an answer T8 (7) starting at time Task 8 is done by Select an answer starting at time T9 (11) T10 (2) End ♂