A project consists of activities P, Q, R and S. The anticipated durations and budgeted cost of these activities is as follows: Activity Duration (days) Total Cost ($) P 15 30,000 Q 10 40,000 R 11 25,000 S 15 35,000 The status of a project at a particular point in time is as follows: Activity % Complete Actual Cost P 100 32,000 Q 100 39,000 R 83 21,000 S 0 0 What is this project's current Cost Performance Index