You as Project Manager are expected to calculate the Percent Complete Indexes by indicating how much
of the work accomplished represents of the total budgeted and actual dollars to date by using the
following formula (please choose 2 correct answers)
Select the correct response(s)
BAC=EV/EAC
BAC = AC / BAC
PCIB = EV / BAC
PCIB = AC / EAC
PCIC = EV / BAC
PCIC=AC / EAC