your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: pv: $1,200,000, ev: $1,000,000, ac: $1,200,000 you expect the underestimation to influence the future as much as it did in the past. if the value of the remaining work (bac - ev) is at $1,000,000, what should be your new eac (estimate at completion)? group of answer choices $1,800,000 $2,000,000 $2,200,000 $2,400,000